County BoardTop story
Eau Claire County committee backs a 12-month pause on new data center applications
The pause covers seven towns for up to a year
- 5-0
- committee vote Tuesday to recommend the pause
- 12 months
- the longest the pause would last
- 7
- towns under county zoning it would cover
- 1,700 acres
- of industrial land where code allows data centers
Sources: News8000, Leader-Telegram
If you live in one of the towns under county zoning, this one's yours. Eau Claire County's Planning and Development Committee voted 5-0 Tuesday to recommend a pause of up to 12 months on new data center applications. The pause would also cover zoning, building and conditional-use permits for those projects.
- Not covered: the city of Eau Claire, Altoona and Fall Creek
- Also covers cloud, AI, data storage and crypto facilities
- County Board first reading Dec. 15, with a vote in January
- Cost: the county's fact sheet lists no fiscal impact
The moratorium would not prohibit future data centers, and it would end automatically if permanent rules take effect first. The Leader-Telegram reported that current code allows them in two districts, which include 1,700 acres of heavy and light industrial land.
The County Board takes up the pause in December and January
- Nov. 17Planning and Development Committee votes 5-0 to recommend the moratorium.
- Dec. 15County Board takes up the measure for a first reading.
- Jan. 2027County Board second reading and vote are expected.
Sources: News8000, Leader-Telegram
“Data centers do come in different sizes. We hear much of the data centers that might be of the larger nature, but there are smaller ones, and impacts can be from small to large.”
Rod Eslinger, Eau Claire County director of Planning and Development